Power unit No 9 330 MWt of Novocherkassk SDPP, Rostov Region

2010 to 2016

Client: OGK-2

General contractor: VIS Group

Power unit No.9 of 330 MW is truly unique for Russia. At the free area of the station a new power unit of 330 MW has been built with the installation of a boiler with a circulating fluidized bed (CFB). This is the first power unit of domestic production in Russia using the CFB technology, which is the best solution in terms of current environmental regulations and meets the requirements of applicable European standards on emissions of harmful substances.

The project also included the following works: expansion of the existing coal yard up to 400,000 tons; construction of a new conveyor gallery of fuel supply towards the new unit; installation of an extra car dumper.

Acting as the general contractor for this innovative project, the Group performed the full range of construction, installation and commissioning works, including the acquisition of auxiliary equipment and its commissioning.