15.11.2024
The production schedule provides for the installation of up to 50 bored piles for the bridge supports on the left bank by the end of the year, 16 of which have been installed to date.
|
|
13.11.2024
Most of them visited the site for the first time and were surprised by the colossal scale of the cultural cluster.
|
|
11.11.2024
Some of the work was carried out at night, so as not to interfere with the traffic flow.
|
|
08.11.2024
As of today, all construction work and finishing work have been completed in the six-story building, engineering equipment has been installed.
|
|
08.11.2024
Today, over 300 people and 12 units of equipment are engaged on VIS Group’s construction site.
|
|
06.11.2024
Cofferdams are steel structures that will create a dry working area for the construction of bridge pylons in the riverbed.
|
|
02.11.2024
During the construction process, the center was repurposed from helping children and adolescents from disadvantaged families to serving people of all ages.
|
|
31.10.2024
The construction is being carried out under the strict supervision of VIS Group specialists, the design institute and experts from ROSDORNII.
|
|