17.01.2025
At the moment, 1,574 of the planned 4,521 tons of metal structures have been produced as of the moment, of which 765 tons have already been shipped from the factory in Tyumen.
|
|
16.01.2025
The Governor of the Moscow Region Andrei Vorobyov familiarized himself with the progress of construction.
|
|
13.01.2025
Concreting of the 53rd bored pile has been completed on the left riverbank.
|
|
11.01.2025
The new cultural cluster will become not only a symbol of modern Yakutsk, but also a key platform for preserving the national epics and culture.
|
|
10.01.2025
A total of over 6,000 m3 of concrete have been poured.
|
|
09.01.2025
In the first days of 2025, motorists used the new road 157,631 times.
|
|