Three PPP polyclinics under construction in Novosibirsk are close to completion
13.04.2023
The construction readiness of the first three facilities of VIS Group’s PPP project is 67-74%.
The subgrade of the Mytishchi high-speed chord under construction is 85% ready
12.04.2023
This is one of the largest transport projects in the Moscow region, which is being realized under concession terms.
All bridge concession facilities in Novosibirsk are over 67% ready
10.04.2023
More than 1,200 people and 160 pieces of equipment are employed by VIS Group in the construction of transport infrastructure facilities under a concession project.
Deputies of the State Duma of the Russian Federation and the Legislative Assembly of the Novosibirsk Region monitor the implementation of the PPP project in Novosibirsk
06.04.2023
Under a PPP agreement, VIS Group is building seven modern polyclinic complexes in the capital of Siberia simultaneously.
Expert RA assigns a ruA credit rating to OOO VIS FINANCE bonds
04.04.2023
Since 2017, the holding has been actively working on the securities market.
Construction readiness of the three polyclinics of the PPP project in Novosibirsk ranges between 55 and 72%
29.03.2023
Over 750 people are currently engaged in construction, and work is underway at all sites.
VIS Group completes the construction of a cable-stayed bridge pylon in Novosibirsk
27.03.2023
The pylon’s right and left pillars reached the design height of 114 meters. In total, 10,312 m3 of concrete was poured into the pylon’s monolithic body.
Youth festival supported by VIS Group gathers over 8,000 people
26.03.2023
Support for social initiatives in the regions where it operates is an important activity for VIS Group.