45% of the first layer of asphalt concrete on the Mytishchi high-speed chord under construction has been laid
22.06.2023
To date, the first, 16-cm layer of asphalt concrete has been laid over 7.5 km.
26 cables were mounted by the builders of the bridge across the Ob in Novosibirsk
20.06.2023
Installation of a cable-stayed system with 70 cables is a complex technological process that began in early May with the pairwise tensioning of the shortest cables.
VIS Group submits the revised part of the Lensky Bridge project in Yakutia for consideration by Glavgosexpertiza
08.06.2023
The documentation has already passed entrance control.
“It’s an impressive medical center”: Russian State Duma deputy Oleg Ivaninsky visits one of the seven PPP clinics under construction in Novosibirsk
07.06.2023
The first three polyclinics are already at the final stage of construction.
New cultural cluster will give impetus to the development of creative life in Yakutia
05.06.2023
“I think that there is no building on par with this one in the entire Russian Far East. It is unique in that it integrates our ethnicity, traditions and modernity,” Marina Silina, Deputy Minister of Culture and Spiritual Development of Yakutia.
VIS Group starts laying asphalt concrete at the right-bank junction of the bridge over the Ob River in Novosibirsk
02.06.2023
The first 360 tons of asphalt concrete mixture have been laid in an area of 2,300 out of 6,000 m2.
Head of Yakutia assesses the progress of the cultural cluster construction
01.06.2023
On the first day of summer, the Head of the Republic of Sakha (Yakutia) Aysen Nikolaev visited the construction site of the complex of the State Philharmonic and Center for Epic Literature and the Arts being built in Yakutsk.
First 10 cables are mounted on the bridge pylon in Novosibirsk
30.05.2023
Ten cables over 73 meters long and weighing 3.7 tons each are installed in the design position, and their fastenings and tensioning are being adjusted.