The Doverie rehabilitation center in Salekhard will be outfitted with equipment unique to Yamal. The Governor of Yamal assessed the degree of readiness of the facility, the construction of which is being completed by VIS Group
28.09.2023
Today the overall readiness of the three-story building is estimated at 93%.
VIS Group continues the construction of a water treatment complex as part of the National Project “Ecology” in Solnechnogorsk
26.09.2023
The degree of readiness of the utility infrastructure facility is about 30%.
Painting the 114-meter pylon of the bridge under construction in Novosibirsk will require 9 tons of special paint
25.09.2023
As a result of ongoing multi-layer painting, it will become pearly white.
The construction of a monolithic frame of one more PPP clinic in Novosibirsk is almost completed
19.09.2023
To date, the construction of the building’s monolithic frame has been completed by 99%.
Cast asphalt is being laid on the cable-stayed section of a bridge under construction in Novosibirsk
19.09.2023
The installation of road pavement on the spans of the 380-meter cable-stayed bridge began after the completion of cable installation.
Top asphalt layer is being placed on the Mytishchi Expressway under construction
15.09.2023
Currently, this work has been completed on a 3.5-kilometer section of the road.
An agreement is signed between VIS Group and the Trans-Baikal Territory at the Eastern Economic Forum
12.09.2023
The document was signed by the Governor of the Trans-Baikal Territory Alexander Osipov and Deputy CEO of VIS Group Artyom Melikhov.
VIS Group received a positive conclusion from the Glavgosexpertiza on the project documentation for the Lena Bridge
09.09.2023
VIS Group has begun preparing the paperwork to obtain a construction permit.